At 16 o'clock on the afternoon of May 16, the first wind turbine of Xinjiang Ronghe Power Station invested by the Electric Power Construction Group was connected to the grid for power generation.
Xinjiang Ronghe Power Station is the first national military-civilian integrated renewable energy LAN project. It is a local area network project integrating “wind, light, firewood and storage”. It is also the most complicated domestic technology, the worst operating environment and the largest installed capacity. Renewable energy LAN system.
Since the project started construction on August 18, 2018, the new energy company has actively coordinated the participating units, overcoming a series of plateau construction problems such as altitude sickness, transportation difficulties, and tight construction period, and has overcome the construction of plateau independent microgrid and multiple power sources. A number of technical bottlenecks in operation control, on December 26, 2018, the project was connected to the grid for power generation.
The successful integration of the first wind turbine group marked the completion of the renewable energy LAN construction task by the new energy company, and accumulated valuable experience for the subsequent construction and operation of the local area network, and expanded the new business field for the Group. The national military-civilian integration strategy has made positive contributions.
The new energy company will make persistent efforts to further accelerate the progress. It is planned to realize all the wind turbines to be put into operation before May 20, undertake the operation and maintenance of the power grid, provide long-term, efficient and stable clean energy services for the border guards, and effectively serve the plateau frontiers and civilians.