4 new railway projects in Guizhou will start in 2021
Date:2021-03-12 origin:RCCN Visit:10672
Among them, the infrastructure category includes 9 railway projects in total, including the renewal of the Guiyang-Nanning Railway, the newly built Xuyong-Bijie section of the Longhuang Railway, and the Panxian-Xingyi Railway. Construction of the newly constructed Gui'an New District Railway There are 4 projects such as the relocation project of Huchao-Qingzhen section of the Hulin branch line, the north-south extension of the Wengma Railway, the Tongren-Jishou Railway, and the speed-up transformation of the Guiyang-Guangzhou Railway; two preliminary projects include the Zunyi-Luzhou Railway and the Dacun-Zunyi Railway.
3 continued projects
The newly-built main line of Guiyang-Nanning Railway is 481 kilometers long, of which the Guizhou section is about 200 kilometers, with five passenger stations in Longlibei, Guiding County, Duyundong, Dushandong, and Libo, with a design speed of 350 kilometers per hour. Construction started on the whole line in December 2017 and is expected to be completed and opened to traffic in December 2023;
The new main line of Panxian-Xingyi Railway has a total length of 98.3 kilometers and a design speed of 250 kilometers per hour. There are 3 stations on the whole line. Panzhou Station will be rebuilt, and Baotian Station and Xingyi South Station will be newly built. The project investment is estimated at 16.1 billion yuan, and it is expected to be completed and opened to traffic in 2024;
The new line from Xuyong to Bijie on the Longhuang Railway is 189.3 kilometers long, with 14 stations including Xuyongbei, Weixin, Yile, and Bijiedong on the whole line. The project started construction in October 2016 and is scheduled to be completed and opened to traffic in 2022.
4 new projects
The north-south extension line of Wengma Railway starts from Gelaoba Station of Chuan-Guizhou Railway in the north to Duyun Station of Qian-Gui Railway in the south. The length of the line is 219 kilometers. , One of the first phase of the project (Wengma Line), the Shanghai-Kunming Line Fuquan Station Kaili end additional Jiangjiaping station lead, north to the vicinity of Weng'an County, the main line is 64.1 kilometers long, officially opened for operation on January 23, 2021; In the project, the north extension line (Wengzun Line) is connected to Ge Laoba Station of the Sichuan-Guizhou Railway, with a total length of 99.6 kilometers; the south extension line (Madu Line) is connected to the Xinduyun Station under construction on the Qiangui Line, with a total length of 39.5 kilometers ;
The Tongren to Jishou Railway starts from the Phoenix Station of Zhangjihuai High-speed Railway under construction and ends at Tongyuchang of Tongren Station. The newly-built main line has a total length of 52.9 kilometers, of which the Guizhou section is 18.94 kilometers, and the new Tongren North Station is established. The design speed is 250 km/h. The total planned investment is 7.803 billion yuan. The feasibility study of the project has been completed. The preliminary work such as planning and site selection, pre-examination of land use, environmental assessment, soil and water conservation, social stability risk assessment, and prospecting (fixed survey) is being carried out in an orderly manner. The planned construction period is 3 years.
The speed-up transformation of the Guiyang-Guangzhou Railway (Gui-Guang High-speed Railway) is an important component of my country’s “Eight Vertical and Eight Horizontal” high-speed railway network, Lan (West) and Guangzhou Passage. , The operating speed is 250 kilometers/hour, and the conditions for speed increase of 300 kilometers/hour are reserved, and the whole line will be opened to traffic on December 26, 2014. It is planned to increase the operating speed from the current 250 kilometers to 300 kilometers per hour. After the speed increase, the time from Guiyang north to Guangzhou south will be shortened from 4 hours and 10 minutes to about 3 hours and 30 minutes from the existing benchmark car.
The relocation project of the Huchao-Qingzhen section of the Hulin branch line of the railway will be reconstructed. The new line starts from the Shibanshao station of the Shanghai-Kunming Railway and connects to the existing Huhao branch line to build the Qingzhen North Station. The total length of the relocation project is 33.952km, of which the new main line is 24.540km; the Shanghai-Kunming railway is 6.828km; the Shibanshao station and Qingzhen station are rebuilt; the Qingzhen north to Qingzhen connecting line is 1.529km; the new Qingzhen The connecting line to the mountain forest side line is 0.651km long; the rebuilt Huhao branch line is 0.404km long.
2 preliminary items
The railway from Zunyi to Luzhou is about 236 kilometers, including 52 kilometers in Sichuan Province and 184 kilometers in Guizhou Province. It is proposed to set up 5 stations including Chishui, Xishui, Renhuai, Maoshi, Zunyi, and the design target speed is 350 kilometers per hour. hour.
The freight railway from Zunyi to Gulin Dacun starts from Xuyong to Dacun Station on the Dacun Railway and ends at Gelaoba Station on the Chuan-Guizhou Railway, connecting with the northern extension of the Wengma Railway. The total length of the line is about 110 kilometers, with a total investment of 6 billion yuan (95 kilometers in Guizhou, with an estimated investment of 5 billion yuan). The railway is classified as Class II railway, with a design speed of 120 km/h.
Article information source-Guizhou Provincial Development and Reform Commission
Disclaimer: Part of the public information collected on this website comes from the Internet. The purpose of reprinting is to convey more information and use it for network sharing. The content of the article is for reference only and does not constitute any investment or other advice. If you find that there are works on the website that infringe your intellectual property rights, please contact us and we will modify or delete them in time.
Related articles
-
线槽的作用及叫法
线槽的作用及叫法
-
2009第四届中国(上海)国际母线线槽及桥架工业展览会
金属线槽、镀锡母线槽、铝合金母线槽、钢外壳母线槽、组合式线槽、防碾压踩踏线槽 、机械设备配电线槽、电话线槽、PVC线槽、地板线槽、插接母线线槽、微动力及照明母线槽、高中低压电流空气式绝缘插接母线槽、带散热片密集型绝缘插接式线槽、全封闭树脂浇注母线槽(防水、防火、防腐母线槽)、共箱高低压母线槽及轨道交通专用线槽等周边相关加工配套产品。
-
线槽规格和品种以及线缆的敷设
线槽规格和品种以及线缆的敷设
-
低烟无卤阻燃型走线槽
低烟无卤阻燃型走线槽
-
PVC线槽的安装-综合布线
线槽安装时,应注意与强电线槽的隔离。布线系统应避免与强电线路在无屏蔽、距离小于20cm情况下平行走3米以上。如果无法避免,该段线槽需采取屏蔽隔离措施。进入家具的电缆管线由最近的吊顶线槽沿隔墙下到地面,并从地面镗槽埋管到家具隔断下。
-
线槽用PVC是什么材料
在塑料制品中,线槽的主要原料是PVC.
-
线槽规格
线槽规格,上海日成-RCCN,专业制造线槽,技术团队及丰富经验,提供PVC线槽、行线槽、配线槽在工业设计、机械设计等配电柜综合布线解决方案.专业服务于外资及国内品牌有线槽需求的企业,产品通过UL,CE,ROHS国际认证.
-
线槽种类
线槽在办公室的安装细节需要要注意的是线槽种类,包括的深度和宽度,因为尺寸不足也会让地面在放线管后不平,到时候只有返工。