Recently, the National Energy Administration issued the Notice on Publishing the Leading Base of Photovoltaic Generation in 2017 and Relevant Requirements
The "Notice" requires that the application leading base should complete the competition and optimization before March 31, 2018, all the construction will be started before June 30, and all the capacity will be completed and connected to the grid before December 31; the leading technology base should complete the competition by April 30, 2018 Preferably, all construction started before March 31, 2019, and all the capacity will be completed and connected to the grid before June 30, 2019.